Starz

Check More Updates
Timelapes Video
2018-03-01
  • Tower-1:  Slab Shuttering works for 14th floor slab is in progress.
  • Tower-1: Block Works layout at 11th floor is in progress
  • Tower-1: Block Works at 10th floor above Lintel Level is in progress
  • Tower-1: Block Works at 9th floor above Lintel Level is in progress
  • Tower-1: Plastering work at 4th ,5th and 7th is in progress
  • Tower-1 : Wall Tile work 4th and 5th floor is in progress
  • Tower-1 : False ceiling suspension 1st and 2nd is in progress
  • Tower-2: Core Wall & Column Shuttering works for 15th Roof floor Slab is in progress.
  • Tower-2: Reinforcement works for 15th floor slab casted on 24.02.2018
  • Tower-2: Block Works layout at 13th floor is in progress
  • Tower-2: Block Works at 12th floor upto Lintel Level is in progress.
  • Tower-2: Block Works at 11th floor upto Lintel Level is in progress.
  • Tower-2: Plastering work at 6th and 7th floor is in progress.
  • Tower-2 : Wall Tile work 6th and 7th floor is in progress
  • Tower-2 : False ceiling suspension 2nd and 3rd is in progress
  • Tower-2: Water proofing for wet area 1st is in progress
  • Ceiling plastering works at Ground floor is in progress
  • Plastering works at podium-1 & podium-2 is in progress
  • Preparation for Epoxy Flooring @ Podium-1 & Podium-2 is in progress
2018-02-15
  • Ceiling plastering works at Ground Floor is in progress
  • Preparation for Epoxy Flooring @ Podium-1 & Podium-2 is in progress.
  • Tower-1: Plastering work at 3rd to 5th floor is in progress.
  • Tower-1: Block works at 8th & 9th floor is in progress.
  • Tower-1: Bathroom wall tile works at 1st & 2nd floor is in progress.
  • Tower-1: Shuttering works for 13th floor PT Slab is in progress.
  • Tower-2: Bathroom wall tile works at 2nd, 3rd & 4th floor is in progress.
  • Tower-2: Plaster Works at 5th & 6th floor is in progress.
  • Tower-2: Block Works at 8th, 9th & 10th floor is in progress.
  • Tower-2: Columns & Core wall Shuttering works for 14th to 15th floor is in progress.

WALKTHROUGH VIDEO