Resortz

Check More Updates
Timelapes Video
2018-03-01
  • Construction NOC for foundation works received.
  • Obtained NOC for office setup and mobilization of site office completed.
  • PCC 100% work completed.
  • Block work for shoring 100% completed.
  • Water proofing works 80% completed.
  • Block no 3:
    • Raft completed.
    • Retaining wall completed.
    • Columns /Shear walls for Basement to Ground floor casting in progress.
    • Tower crane erection completed.
    • Ground floor slab decking in progress and reinforcement works started.
  • Block no 2:
    • Raft completed.
    • Waterproofing for retaining walls in progress.
    • Tower crane erection completed.
    • Vertical elements reinforcement in progress.
  • Block no 1:
    • Raft Reinforcement in progress and awaiting DM inspection.
    • Waterproofing for retaining wall in progress.
    • Tower crane erection completed.
2018-02-15

Block no 1 :

  • Raft Reinforcement in progress.
  • Waterproofing for retaining wall in progress.
  • Tower crane erection completed.

Block no 2 :

  • Raft Reinforcement completed awaiting DM approval for casting.
  • Waterproofing for retaining walls in progress.
  • Tower crane erection completed.

 

  • Construction NOC for foundation works received.
  • Main contract awarded to M/s Dubai Walls and obtained NOC for office setup and mobilization of site office completed.
  • PCC 100% work completed.
  • Block work for shoring 95% completed.
  • Water proofing works 75% completed.

Block no 3 :

  • Raft completed
  • Retaining wall in progress.
  • Columns /Shear walls for Basement to Ground floor casting in progress.
  • Tower crane erection completed.

WALKTHROUGH VIDEO

PROJECT LOCATION