2018-03-01
  • Submission for TIS approval done in RTA and approved.
  • Main Construction Contract awarded to M/s Naresco and mobilization completed.
  • Dewatering in progress.
  • PCC 90% completed.
  • Shoring block work 90% completed and guniting completed
  • Waterproofing works 60% completed.
  • Reinforcement for Raft fabrication in progress.
  • Tower crane erection completed and second tower crane foundation casted.
  • Water tank and Sump pit Raft casted .
2018-02-15
  • Submission for TIS approval done in RTA and approved.
  • Main Construction Contract awarded to M/s Naresco and mobilization completed.
  • Building permit obtained on 9/10/17.
  • Dewatering in progress.
  • PCC 80% completed.
  • Shoring block work 80% completed.
  • Waterproofing works 50% completed.
  • Reinforcement for Raft fabrication in progress.
  • Tower crane erection completed.
  • Water tank waterproofing in progress.