2018-03-01
  • Aluminum doors & windows installation completed, Final sealant works in progress.
  • External Plaster works 100% completed.
  • External and Internal painting works in (7th and 8th floor) progress.
  • Swimming pool landscape and WPC flooring completed.
  • ACP cladding snag in progress.
  • Kitchen installation & Snag Work in progress.
  • Landscape works planting in progress.
  • Basketball and tennis court fencing and flood light installation done.
  • Basketball court sport flooring works in progress.
  • Main entrance wall cladding completed and canopy installation completed.
  • Basement car park coating completed and signage’s installation in progress.
  • Swimming pool BBQ area Pergola completed, Planter area pergola completed.
  • Installation of Light fittings/Sanitary fittings in progress.
  • Installation of landscape lighting in progress and water feature in landscape completed.
  • Main entrance sliding door /Automatic door installed and ACP ceiling for main entrance foyer in completed.
  • Sitting area/party hall painting/main entrance lobby decorative painting completed.
  • Drive way ground floor coating completed.
  • Decorative painting works in corridor in progress.
  • Main access for project completed.
  • Permanent building cleaning equipment installed.
  •   Snag works in progress.
2018-02-15
  • Aluminium doors & windows installation completed, Final sealant works in progress.
  • External Plaster works 100% completed.
  • Swimming pool landscape and WPC flooring completed.
  •  ACP cladding snag in progress.
  • Kitchen installation & Snag Work in progress
  • Landscape works planting in progress.
  • Basketball and tennis court fencing and flood light installation done.
  • Main entrance wall cladding completed and canopy installation completed.
  • Basement car park coating completed and signage’s installation in progress
  • Swimming pool BBQ area Pergola completed, Planter area pergola completed.
  • Installation of Light fittings/Sanitary fittings in progress.
  • Installation of landscape lighting in progress and water feature in landscape completed.
  • Main entrance sliding door /Automatic door installed and ACP ceiling for main entrance foyer in completed.
  • Sitting area/party hall painting/main entrance lobby decorative painting completed.
  • Drive way ground floor coating completed.
  • Decorative painting works in corridor in progress.
  • Main access for project completed.
  • Permanent building cleaning equipment installed.
  • Snag works in progress