Timelapes Video
2017-12-15
  • 23 no of apartment handed over to owner/End user.
  • Snags identified by Owners is being actioned.
2017-11-15
  • Handing over of apartments to owners has been started.
  • Building Completed ? Building Completion Certificate received from DCCA.
  • Dubai Civil Defense Certificate received.
  • HVAC Testing & Commission is Completed.
  • Deep Cleaning in Progress.
  • Snag in Progress.
  • DEWA Transformer & Cable installation is completed.