2018-03-01
  • 15th floor, cover slab for PART A & PART B has completed.
  • Roof floor Tower A slab shuttering work is in progress.
  • Electrical PVC Wall conduiting up to 5th floor has completed and progressing well on 6th & 7th floor.
  • Ceiling Surface preparation at basement, GF completed and podium levels is in progress.
  • Concrete Masonry work at Basement, to 9th floor has been completed and progressing well on 10th,  11th  & 12th floor.
  • Internal plastering work has completed up to 3rd floor and progressing well on 4th & 5th floor.
  • Wet Areas tiling work is progressing well on 1st & 2nd floor.
  • HVAC, FCU installation has started and progressing well.
2018-02-15
  • 13th floor, cover slab for PART A & PART B has completed.
  • 14th floor Tower A slab has been casted and Tower B is under progress.
  • Electrical PVC Wall conduiting up to 3rd floor has completed and progressing well on 4th & 5th floor.
  • Ceiling Surface preparation at basement, GF completed and podium levels is in progress.
  •  Concrete Masonry work at Basement, to 6th floor has been completed and progressing well on 7th, 8th & 9th floor.
  • · Internal plastering work has completed on 1st floor and progressing well on 2nd & 3rd floor.
  • Wet Areas tiling work has started on first floor.
  • HVAC, FCU installation has started and progressing well.