Dreamz

Check More Updates
Timelapes Video
2018-03-01
  • Individual water meters and electric meters has been delivered and installed for all villas.
  • All 04 No’s Pocket substation has been commissioned by DEWA.
  • LV cabling work has been completed.
  • HV cabling work has completed for all plots.
  • BCC from TRAKHEES has been successfully obtained for all 47 Plots.
  • NCC received for all plots.
  • DCD completion certificate has been received for all 47 Plots.
  • LPG approval has been obtained for 25 Plots.
  • Major Snagging and De-snagging work is completed in Zone 1&2 and 3.
  • Feeder Pillar Installation work has been completed for all 47 plots.
  • Feeder Pillar Termination work has been completed for 30 Plots and progressing well in remaining plots.
  • Roads, Street lights and FIC connection is completed.
  • Testing & Commissioning has been completed for all 171 villa’s.
2018-02-15
  • DEWA pocket substation has been delivered at site and installed successfully.
  • All 04 No’s Pocket substation has been commissioned by DEWA.
  • LV cabling work has been completed.
  • HV cabling work has completed for all plots.
  • BCC from TRAKHEES has been successfully obtained for all 47 Plots.
  • NCC received for all plots.
  • DCD completion certificate has been received for all 47 Plots.
  • LPG approval has been obtained for 23 Plots.
  • Major Snagging and De-snagging work is completed in Zone 1&2 and 3.
  • Feeder Pillar Installation work has been completed for all 47 plots.
  • Feeder Pillar Termination work has been completed for 30 Plots and progressing well in remaining plots.
  • Internal Plaster, External plaster, Roof & Wet Areas water proofing, Roof floor tiling and Marble works for Living, Dining & Staircase has been completed for all Zones.
  • Roads, Street lights and FIC connection is completed.
  • Testing & Commissioning has been completed for all 171 villa’s.