2018-03-01
  • Enabling work contractor has been mobilized at site.
  • Soil excavation work has started and progressing well.
  • Guide wall work has been started and progressing well.
  • Preparation of Tender documents is in progress.
  • MEP detail design drawings is in progress.
  • Finalization for piling work contractor is under process.
2018-02-15
  • Soil Investigation is completed.
  • Shoring & Excavation Design Approved by Authority.
  • RTA NOC received.
  • Etisalat & DU NOC has been received.
  • TIS has been approved by RTA.
  • DEWA NOC received.
  • Enabling work contractor has been mobilized at site.
  • Soil excavation work has started and progressing well.
  • Preparation of Tender documents is in progress
  • MEP detail design drawings is in progress